An Audit of Palo Pinto County Municipal Water District No. 1

July 2026

Overview

The Palo Pinto County Municipal Water District No. 1 (District) is unable to complete the construction of the Turkey Peak Reservoir after taking on approximately $94.7 million in bond debt. Without the reservoir, the District's customers, including the City of Mineral Wells, may face water shortages.

The District followed its processes for collecting revenues and processing expenditures, complied with the Texas Water Development Board (TWDB) requirements, and mostly complied with statutory requirements.